  • Supertram Rail Replacement - Area Three - Gleadless Townend to Herdings Park

  • 08/08/2018 12:25:56 Posted:

    Gleadless Townend to Herdings Park

    Area Three of the ongoing tram rail replacement works will begin on Friday 10 August, and continue through to Sunday 19 August.

    Where will trams operate to and from?

    Blue route services will run as normal between Malin Bridge and Halfway
    Yellow route services will run as normal between Meadowhall and Middlewood
    Purple route services will operate a limited service between Catherdral and Gleadless Townend, before diverting to Birley Lane where the service will terminate.

    Halfway Park and Ride

    Will remain open whilst these essential works. During the works parking at the site will be free (customers will just need to buy their ticket to travel on board the tram).

    Replacement Bus Services

    The P3 bus will replace trams between Gleadless Townend and Herdings Park. The bus will depart from the Methodist church at Gleadless Townend, travelling along Norton Avenue to the roundabout, where it doubles back and then turns onto Raeburn Road to serve Herdings. Herdings Park to Gleadless Townend is served via Raeburn Road, Leighton Road, onto Norton Avenue before terminating at Gleadless Townend Methodist church. Full route map can be found here and timetables here.

  • Supertram Rail Replacement Scheme 2018

  • 18/06/2018 09:48:34 Posted:

    Supertram Rail Replacement Scheme
    The engineering work to replace sections of worn-out Supertram tram tracks starts on Saturday 26th May on the tram route between Hillsborough and Middlewood. The new rail will improve passenger comfort and reduce noise in areas where the track is worn. VolkerRail has once again been successful in winning the contract for the next three years of the rail replacement project.

    Stage Ones is between May 2018 and September 2018.
    Each stage will be split into areas covering different sites across the network to minimise passenger disruption. Works in Area 1, Hillsborough – Middlewood, will begin on Saturday 26th May with some preparatory works taking place overnight from Monday 21st May.
    The proposed dates are:
    Area 1 Hillsborough - Middlewood: Saturday 26th May to Sunday 17th June
    Area 2 Birley Lane - Halfway: Saturday 23rd June to Wednesday 8th August 
    Area 3 Gleadless Townend – Herdings Park: Friday 10th August to Sunday 19th August
    Area 4 Gleadless Townend – Halfway/Herding Park: Saturday 25th August to Sunday 2nd September, plus Saturday 8th & Sunday 9th September
    Area 5 Donetsk Way-Halfway: Monday 10th September to Friday 14th September

    Stage Two: summer 2019 (dates to be confirmed);

    Stage Three: summer 2020 (dates to be confirmed).